78
Global
Height rank

DAMAC Heights

Dubai
Height 335.1 m / 1,099 ft
Floors 88
Official Name
The current legal building name.

DAMAC Heights

Other Names
Other names the building has commonly been known as, including former names, common informal names, local names, etc.

DAMAC Residenze

Type
CTBUH collects data on two major types of tall structures: 'Buildings' and 'Telecommunications / Observation Towers.' A 'Building' is a structure where at least 50% of the height is occupied by usable floor area. A 'Telecommunications / Observation Tower' is a structure where less than 50% of the structure's height is occupied by usable floor area. Only 'Buildings' are eligible for the CTBUH 'Tallest Buildings' lists.

Building

Status
Completed
Architecturally Topped Out
Structurally Topped Out
Under Construction
Proposed
On Hold
Never Completed
Vision
Competition Entry
Canceled
Proposed Renovation
Under Renovation
Renovated
Under Demolition
Demolished

Completed, 2018

Country
The CTBUH follows the United Nations's definition of Country, and thus uses the lists and codes established by that organization.

United Arab Emirates

City
The CTBUH follows the United Nations's definition of City, and thus uses the lists and codes established by that organization.

Dubai

Postal Code

337-1500

Function
A single-function tall building is defined as one where 85% or more of its usable floor area is dedicated to a single usage. Thus a building with 90% office floor area would be said to be an "office" building, irrespective of other minor functions it may also contain.

A mixed-use tall building contains two or more functions (or uses), where each of the functions occupy a significant proportion of the tower's total space. Support areas such as car parks and mechanical plant space do not constitute mixed-use functions. Functions are denoted on CTBUH "Tallest Building" lists in descending order, e.g., "hotel/office" indicates hotel function above office function.

residential

Structural Material
Steel
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from steel. Note that a building of steel construction with a floor system of concrete planks or concrete slab on top of steel beams is still considered a “steel” structure as the concrete elements are not acting as the primary structure.

Reinforced Concrete
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from concrete which has been cast in place and utilizes steel reinforcement bars.

Precast Concrete
Both the main vertical/lateral structural elements and the floor spanning system are constructed from steel reinforced concrete which has been precast as individual components and assembled together on-site.

Mixed-Structure
Utilizes distinct systems (e.g. steel, concrete, timber), one on top of the other. For example, a steel/concrete indicates a steel structural system located on top of a concrete structural system, with the opposite true of concrete/steel.

Composite
A combination of materials (e.g. steel, concrete, timber) are used together in the main structural elements. Examples include buildings which utilize: steel columns with a floor system of reinforced concrete beams; a steel frame system with a concrete core; concrete-encased steel columns; concrete-filled steel tubes; etc. Where known, the CTBUH database breaks out the materials used in a composite building’s core, columns, and floor spanning separately.

concrete

Official Website

DAMAC Residenze

Height
Architectural
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building, including spires, but not including antennae, signage, flag poles or other functional-technical equipment. This measurement is the most widely utilized and is employed to define the Council on Tall Buildings and Urban Habitat (CTBUH) rankings of the "World's Tallest Buildings."

335.1 m / 1,099 ft

To Tip
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element (i.e., including antennae, flagpoles, signage and other functional-technical equipment).
335.1 m / 1,099 ft
Occupied
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest occupied floor within the building.
292.3 m / 959 ft
Floors Above Ground
The number of floors above ground should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines should not be included if they have a significantly smaller floor area than the major floors below. Similarly, mechanical penthouses or plant rooms protruding above the general roof area should not be counted. Note: CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (e.g., the level 4, 14, 24, etc. in Hong Kong).

88

Floors Below Ground
The number of floors below ground should include all major floors located below the ground floor level.

5

# of Apartments
Number of Apartments refers to the total number of residential units (including both rental units and condominiums) contained within a particular building.

640

# of Parking Spaces
Number of Parking Spaces refers to the total number of car parking spaces contained within a particular building.

710

Tower GFA
Tower GFA refers to the total gross floor area within the tower footprint, not including adjoining podiums, connected buildings or other towers within the development.

89,579 m² / 964,220 ft²

Rankings
#
78
Tallest in the World
#
16
Tallest in Middle East
#
14
Tallest in United Arab Emirates
#
12
Tallest in Dubai
#
9
Tallest Residential Building in the World
#
6
Tallest Residential Building in Middle East
#
6
Tallest Residential Building in United Arab Emirates
#
5
Tallest Residential Building in Dubai
#
23
Tallest Concrete Building in the World
#
12
Tallest Concrete Building in Middle East
#
11
Tallest Concrete Building in United Arab Emirates
#
9
Tallest Concrete Building in Dubai
Construction Schedule
2006

Proposed

2011

Construction Start

2018

Completed

Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Geotechnical
Wind
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Paint/Coating
Owner/Developer
DAMAC Gulf Properties L.L.C.
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Architect of Record

Usually takes on the balance of the architectural effort not executed by the "Design Architect," typically responsible for the construction documents, conforming to local codes, etc. May often be referred to as "Executive," "Associate," or "Local" Architect, however, for consistency CTBUH uses the term "Architect of Record" exclusively.

AECOM
Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Engineer of Record

The Engineer of Record takes the balance of the engineering effort not executed by the “Design Engineer,” typically responsible for construction documents, conforming to local codes, etc.

AECOM
MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Engineer of Record

The Engineer of Record takes the balance of the engineering effort not executed by the “Design Engineer,” typically responsible for construction documents, conforming to local codes, etc.

AECOM
Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Arabtec
Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Geotechnical
Interiors
FENDI Casa; JC Maclean
Landscape
WAHO
Wind
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Cladding
Alico
Elevator
Toshiba Elevator and Building Systems Corporation (TELC)
Façade Maintenance Equipment
Danway LLC
HVAC
Remco
Paint/Coating

CTBUH Initiatives

CTBUH Releases Year in Review: Tall Trends of 2018

12 December 2018 - CTBUH News

Top Company Rankings: The World’s 100 Tallest Buildings

13 October 2016 - CTBUH Research

Research

12 December 2018

Year in Review: Tall Trends of 2018

CTBUH Research

The astronomical growth in tall building construction observed over the past decade continued in 2018, though the total number of completed buildings of 200 meters’...

About DAMAC Heights

Located in one of the last available plots in the Dubai Marina, a three kilometer stretch of reclaimed land along the Persian Gulf, DAMAC Heights provides a sense of formal interplay with its immediate neighbor, the twisting Cayan Tower. The spatial requirements for units up to the 60th floor required a unique design approach, resulting in a tower that establishes an entirely novel exercise of built expression in the City of Gold.

Each of the tower’s elevations has a unique character and impact upon the surrounding urban environment. From the northwest, the building appears as two smooth blades rising side-by-side from the ground, gently meandering upward to form a sharp convexity, creating the illusion that the building vanishes into the sky for those standing at the base. From the northeast and southwest, the building takes a wider stance—one that is enhanced by a series of horizontal balconies that generate an aesthetic regularity continuing for most of its height. Near the top, the tempo of horizontal elements gives way to seamless, uninterrupted volumes of blue reflective cladding. The elliptical shape of the tower improves views past its densely located neighbors, affording glimpses of the nearby Palm Jumeirah mega-development.

Notable not only for its exterior, DAMAC Heights’s interior spaces offer an impressive assortment of material and color choices: from cool palettes of blue with dark wooden features, to bright sunny spaces strewn in gold curtains, and open floor plans. In an architectural statement that reflects the imperatives of Dubai, and the UAE as a whole, this tower is ready to welcome the next generation of residents in a city that is constantly reinventing itself.

12 December 2018

CTBUH Releases Year in Review: Tall Trends of 2018

The astronomical growth in tall building construction observed over the past decade continued in 2018, though the total number of completed buildings of 200 meters’ or greater height leveled off at 143, after hitting an all-time record of 147 in 2017.

13 October 2016

Top Company Rankings: The World’s 100 Tallest Buildings

The Council is pleased to announce the Top Company Rankings for numerous disciplines as derived from the list of projects appearing in 100 of the World’s Tallest Buildings.