3244
Global
Height rank

Soyak Kristalkule | Finansbank Headquarters

Istanbul
Height 169.0 m / 554 ft
Floors 32
Official Name
The current legal building name.

Soyak Kristalkule | Finansbank Headquarters

Other Names
Other names the building has commonly been known as, including former names, common informal names, local names, etc.

Soyak Plaza, Crystal Tower, Soyak Tower, Soyak Kristalkule

Type
CTBUH collects data on two major types of tall structures: 'Buildings' and 'Telecommunications / Observation Towers.' A 'Building' is a structure where at least 50% of the height is occupied by usable floor area. A 'Telecommunications / Observation Tower' is a structure where less than 50% of the structure's height is occupied by usable floor area. Only 'Buildings' are eligible for the CTBUH 'Tallest Buildings' lists.

Building

Status
Completed
Architecturally Topped Out
Structurally Topped Out
Under Construction
Proposed
On Hold
Never Completed
Vision
Competition Entry
Canceled
Proposed Renovation
Under Renovation
Renovated
Under Demolition
Demolished

Completed, 2014

Country
The CTBUH follows the United Nations's definition of Country, and thus uses the lists and codes established by that organization.

Turkey

City
The CTBUH follows the United Nations's definition of City, and thus uses the lists and codes established by that organization.

Istanbul

Postal Code

34394

Function
A single-function tall building is defined as one where 85% or more of its usable floor area is dedicated to a single usage. Thus a building with 90% office floor area would be said to be an "office" building, irrespective of other minor functions it may also contain.

A mixed-use tall building contains two or more functions (or uses), where each of the functions occupy a significant proportion of the tower's total space. Support areas such as car parks and mechanical plant space do not constitute mixed-use functions. Functions are denoted on CTBUH "Tallest Building" lists in descending order, e.g., "hotel/office" indicates hotel function above office function.

office

Structural Material
Steel
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from steel. Note that a building of steel construction with a floor system of concrete planks or concrete slab on top of steel beams is still considered a “steel” structure as the concrete elements are not acting as the primary structure.

Reinforced Concrete
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from concrete which has been cast in place and utilizes steel reinforcement bars.

Precast Concrete
Both the main vertical/lateral structural elements and the floor spanning system are constructed from steel reinforced concrete which has been precast as individual components and assembled together on-site.

Mixed-Structure
Utilizes distinct systems (e.g. steel, concrete, timber), one on top of the other. For example, a steel/concrete indicates a steel structural system located on top of a concrete structural system, with the opposite true of concrete/steel.

Composite
A combination of materials (e.g. steel, concrete, timber) are used together in the main structural elements. Examples include buildings which utilize: steel columns with a floor system of reinforced concrete beams; a steel frame system with a concrete core; concrete-encased steel columns; concrete-filled steel tubes; etc. Where known, the CTBUH database breaks out the materials used in a composite building’s core, columns, and floor spanning separately.

concrete

Energy Label

LEED Silver

Height
Architectural
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building, including spires, but not including antennae, signage, flag poles or other functional-technical equipment. This measurement is the most widely utilized and is employed to define the Council on Tall Buildings and Urban Habitat (CTBUH) rankings of the "World's Tallest Buildings."

169.0 m / 554 ft

To Tip
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element (i.e., including antennae, flagpoles, signage and other functional-technical equipment).
169.0 m / 554 ft
Occupied
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest occupied floor within the building.
140.0 m / 459 ft
Observatory
140.0 m / 459 ft
Helipad
Height, measured from the level of the lowest, significant, open-air, pedestrian entrance, to the building's helipad.
47.6 m / 156 ft
Floors Above Ground
The number of floors above ground should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines should not be included if they have a significantly smaller floor area than the major floors below. Similarly, mechanical penthouses or plant rooms protruding above the general roof area should not be counted. Note: CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (e.g., the level 4, 14, 24, etc. in Hong Kong).

32

Floors Below Ground
The number of floors below ground should include all major floors located below the ground floor level.

8

# of Parking Spaces
Number of Parking Spaces refers to the total number of car parking spaces contained within a particular building.

680

# of Elevators
Number of Elevators refers to the total number of elevator cars (not shafts) contained within a particular building (including public, private and freight elevators).

26

Top Elevator Speed
Top Elevator Speed refers to the top speed capable of being achieved by an elevator within a particular building, measured in meters per second.

7 m/s

Tower GFA
Tower GFA refers to the total gross floor area within the tower footprint, not including adjoining podiums, connected buildings or other towers within the development.

50,400 m² / 542,501 ft²

Rankings
#
3244
Tallest in the World
#
116
Tallest in Europe
#
25
Tallest in Istanbul
#
1386
Tallest Office Building in the World
#
53
Tallest Office Building in Europe
#
8
Tallest Office Building in Turkey
#
7
Tallest Office Building in Istanbul
#
1756
Tallest Concrete Building in the World
#
84
Tallest Concrete Building in Europe
#
28
Tallest Concrete Building in Turkey
#
21
Tallest Concrete Building in Istanbul
Construction Schedule
2005

Proposed

2011

Construction Start

2014

Completed

Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Project Manager

The CTBUH lists a project manager when a specific firm has been commissioned to oversee this aspect of a tall building’s design/construction. When the project management efforts are handled by the developer, main contract, or architect, this field will be omitted.

Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Cladding
Sealants
Owner
Soyak Holding
Developer
Soyak Holding; Soyak Construction and Trading Co.
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Architect of Record

Usually takes on the balance of the architectural effort not executed by the "Design Architect," typically responsible for the construction documents, conforming to local codes, etc. May often be referred to as "Executive," "Associate," or "Local" Architect, however, for consistency CTBUH uses the term "Architect of Record" exclusively.

HAS Architects
Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Engineer of Record

The Engineer of Record takes the balance of the engineering effort not executed by the “Design Engineer,” typically responsible for construction documents, conforming to local codes, etc.

Balkar Civil Engineering
MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Engineer of Record

The Engineer of Record takes the balance of the engineering effort not executed by the “Design Engineer,” typically responsible for construction documents, conforming to local codes, etc.

Dinamik Proje Engineering and Consulting; Enmar Engineering
Project Manager

The CTBUH lists a project manager when a specific firm has been commissioned to oversee this aspect of a tall building’s design/construction. When the project management efforts are handled by the developer, main contract, or architect, this field will be omitted.

Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Soyak Construction and Trading Co.; Koray Construction, Industry and Trading Co.; Demta Mechanical Construction and Trading; Segatech Electrical Engineering; Johnson Controls
Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Acoustics
SEY Danışmanlık; Cerami & Associates
Energy Concept
Vidaris, Inc.
Environmental
neabranding
Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Fire
Etik Engineering & Consulting
Geotechnical
ELC Group Engineering and Consulting
Landscape
DS Landscape Architects
LEED
Vidaris, Inc.
Security
Pronet
Way Finding
neabranding
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Cladding
Haz Marble; Hilti AG
Concrete
Gümüştaş A.Ş.
Crane
Soyak
Flooring
Taşça
HVAC
York
Rebar
Kaptan Demir Çelik
Sealants